PV*SOL premium has talked to K2 Base since version 2023 R5, but only one module area at a time: each roof area leaves PV*SOL as a JSON file and comes back as a ZIP with the layout, parts list and structural report. AutoCAD gets plans from PV*SOL as DXF, not DWG. Here is where the handover breaks, how to keep it clean, and how to get G99-ready drawings without juggling exports.

In short

  • PV*SOL sends K2 Base exactly one module area per round: location, roof geometry, shading objects, keep-out areas and the module type. The modules are placed in K2 Base, not in PV*SOL.
  • What comes back is a ZIP with the module layout, parts list and structural report. Move a module afterwards and the manufacturer’s calculation no longer applies.
  • Obstacles you only draw in K2 Base never return to PV*SOL, so they are missing from the shading simulation.
  • PV*SOL exports the dimension plan and string diagram as DXF and the circuit diagram as PDF, PNG or SVG. There is no DWG import or export.
  • Running PV*SOL, K2 Base and AutoCAD separately means every change is carried across three times. In the Lion Solar portal you request design, structural calculations and drawings on one screen, with no exports.

We handle PV*SOL design, mounting structures and AutoCAD drawings for installers and EPC contractors, so these three programs are our daily tools. Most of the rework we see does not come from the design itself but from the handovers between them: a roof area moved after the structural report was issued, a chimney that only exists in K2 Base, a DXF that lands in AutoCAD at the wrong scale.

What data moves between PV*SOL, K2 Base and AutoCAD?

There are four handovers between the three programs, and at each one something is lost or has to be redone by hand. This is what actually travels.

DirectionFormatWhat is transferredWhat is missing
PV*SOL → K2 BaseJSON, per module areaLocation, roof geometry, shading objects, keep-out areas, module typeThe layout itself: modules are placed in K2 Base
K2 Base → PV*SOLZIP, per module areaModule layout, parts list, structural reportObstacles added in K2 Base
PV*SOL → AutoCADDXF (dimension plan, string diagram); PDF, PNG, SVG (circuit diagram)2D plan geometryDWG; the circuit diagram as DXF
AutoCAD → PV*SOLImage (scaled) or 3D model (.obj, .dae, .3ds and others)Outline or building geometryDirect DWG import

The real problem is not one file format. It is that there is no shared project: each program holds its own version, and the designer is the interface in between. Sources for the formats are the PV*SOL help pages on the interface to mounting system software and on plans and parts list.

Data flow between PV*SOL, K2 Base and AutoCAD with file formats

Why does each module area go to K2 Base separately?

Because the interface only carries one module area per round. If several areas need the mounting system, you repeat the export and import for each one, and the PV*SOL help says so in as many words. The same applies to the second mounting interface in PV*SOL, the Renusol PV Configurator, available from PV*SOL premium 2025 R6.

One round has six steps: export the area from PV*SOL, open the file in K2 Base, place the modules, run the structural check, download the ZIP and import it back. A pitched roof with two dormers is four rounds; a commercial roof with several planes is more. None of that is hard. It gets expensive when something changes afterwards and every round starts again.

So one habit saves a lot of time: fix the module type before you export the first area. The module type is part of the export file. If the client switches modules after the quote, every area goes through the cycle again.

Exporting a module area from PV*SOL to K2 Base
Exporting a module area from PV*SOL to K2 Base

What happens if the layout changes after the structural check?

Then the structural report describes a different system from the one being built. Valentin states plainly that the module arrangement should not be changed after import, otherwise the manufacturer’s structural analysis becomes invalid.

The trigger is usually harmless. The client wants two more panels after the first quote, or the roofer reports an extra vent. Move a module in PV*SOL and the yield and strings still look right, but the parts list and structural report belong to the old layout, and on site you are short of rails or roof hooks.

Our rule is simple: the import from K2 Base is a sign-off point. After it, nobody touches the layout in PV*SOL. If something changes, only the affected area goes through K2 Base again, and the old report is clearly marked as superseded.

The second trap is obstacles. A chimney drawn only in K2 Base is not sent back to PV*SOL. It is in the structural check but missing from the shading loss calculation. Obstacles always go into PV*SOL first, before the export.

Does the mounting system report cover the roof structure?

No. A K2 Base or Renusol report proves the mounting kit and its fixings against the manufacturer’s data. Whether the rafters, purlins or profiled sheeting can carry the extra load is a separate question, and in the UK it is now a formal one.

Since 18 June 2026, MIS 3002 version 6.0 applies to every MCS-certified solar PV installation. For the first time it requires the roof structure to be checked by a suitably competent person before installation, to confirm it can carry the array. A good assessment treats dead load, wind uplift and snow load as separate cases rather than one combined number (background on MIS 3002 v6.0). The kit report and the roof check answer different questions, and you need both. We cover the details in our guide to structural calculations for solar PV mounting systems.

Can PV*SOL import or export DWG files?

No, PV*SOL supports DWG in neither direction. Both directions still have workarounds that are reliable in practice.

Getting a DWG into PV*SOL: as an image or a 3D model

For site plans and floor plans, an image is the quickest route. Export the plan from AutoCAD as PNG or PDF, load it into PV*SOL as a ground plan and scale it against a known distance such as the eaves line. Then check the scale against a second distance. An error of a few per cent is invisible on screen but shifts a whole row of modules on a 30-metre roof.

For real 3D geometry, PV*SOL reads formats including .obj, .dae, .3ds and .stl. From a DWG, the usual path runs through an intermediate tool such as SketchUp or Blender. For the roof layout side of PV*SOL in a UK context, see our PV*SOL 3D layout guide for UK rooftops.

Getting plans from PV*SOL into AutoCAD: DXF, not DWG

PV*SOL exports the dimension plan and the string diagram as DXF, as well as PDF and PNG. The circuit diagram is only available as PDF, PNG or SVG. Open the DXF in AutoCAD and save it as DWG, then check three things: units and scale, the layer structure against your drawing standard, and whether text and labels came across legibly.

We use the PV*SOL circuit diagram as a starting point only. The single line diagram for the DNO is redrawn in AutoCAD, because it has to show what the G99 application asks for, not what the simulation needs.

Which drawings does a G99 application need?

For systems up to 50 kW, the G99 application uses form A1-1, and the DNO expects a single line diagram with it. A complete pack usually contains:

  • the application form (A1-1 up to 50 kW)
  • an accurate single line diagram
  • protection settings
  • a site plan
  • inverter details with their ENA Type Test Register references
  • the MPAN and a letter of authority

Three of these come straight out of the design chain: the single line diagram, the site plan and the protection settings. If the layout changed after the K2 round and the drawings were not updated, the DNO receives a system that does not match what gets built. Check your own DNO’s page for its exact list, for example Electricity North West’s G99 guidance, and our grid connection approval guide for the wider process.

A clean handover in seven steps

A clean workflow has one source for the geometry, a fixed sign-off point after the structural check and one revision number that runs through every file.

  1. Capture the roof once. Survey, drone flight or 3D model. This geometry is the only source; nobody draws the roof a second time.
  2. Set the module type and obstacles in PV*SOL. Roof windows, vents, chimneys, edge zones. Anything that affects shading goes in before the export.
  3. Name each area clearly. For example “South-1” or “Dormer-West”, identical in PV*SOL, in K2 Base and in the drawing title block.
  4. Send each area to K2 Base on its own. Place the modules, run the mounting structure check and import the ZIP back into PV*SOL.
  5. Freeze the layout. Only now design strings and inverters in PV*SOL and run the simulation.
  6. Derive the drawings. Export the dimension plan and string diagram as DXF, check the scale in AutoCAD, then produce the site plan, string plan and single line diagram. If you are short of time, we can take on the AutoCAD drawings.
  7. Number your revisions. Every change gets an index (A, B, C) that matches in the PV*SOL file, the K2 report and the title block.

No exports: every document from one request

The seven steps work, but every change costs time. That is why we reduced the whole workflow to a single screen in the Lion Solar portal. You tick the documents you need: PV*SOL project and report, site plan, string plan, single line diagram, substructure plan and roof plan, plus structural calculations for K2, Schletter or SL Rack using UK load values. Our engineers produce them and upload them to the same project, versioned with every revision. You export nothing and move nothing between programs.

StepThree separate programsLion Solar portal
RequestSend data and files to several placesRequest every document on one screen
StructureExport each area to K2 BaseChoose K2, Schletter or SL Rack
DrawingsExport DXF, rework in AutoCADSite, string, substructure and roof plans plus single line diagram as DWG
ChangesRepeat in three programs, versions by emailRequest once, every revision versioned in the project

Live demo: get a personal 30-minute live walkthrough of LSS, tailored to your business. Book a live demo

Common mistakes in the handover

  • Layout changed after the K2 import. Yield and strings are right, the structural report and parts list are not. Fix: send the affected area through K2 Base again.
  • Module type switched after export. Every area has to be exported again. Fix: agree the module with the client before the first export.
  • Obstacle drawn only in K2 Base. It is missing from the shading simulation. Fix: always add obstacles in PV*SOL first.
  • DXF used without checking the scale. The drawing looks right, the dimensions are not. Fix: measure two known distances in AutoCAD.
  • Kit report treated as the roof check. Under MIS 3002 v6.0 the roof structure needs its own check by a competent person. Fix: plan the roof assessment alongside the K2 round, not after it.
  • Files shared by email. Installers, structural engineer and DNO application work from different revisions. Fix: one project folder, one revision index for every file.

Frequently asked questions

Can PV*SOL import DWG files?

No, PV*SOL cannot import DWG directly. Load site plans and floor plans as images and scale them against a known distance. For 3D geometry, PV*SOL accepts formats including .obj, .dae, .3ds and .stl; from a DWG, the usual route is through SketchUp or Blender. Always check the scale against a second distance before placing modules.

Can I send several roof areas to K2 Base at once?

No. The interface transfers exactly one module area per round. For several areas, you repeat the export, the layout in K2 Base and the import for each one. Name the areas clearly and fix the module type first, so that a later change does not force you to repeat the cycle for every area.

Which mounting system manufacturers have an interface to PV*SOL?

According to the PV*SOL help, two: K2 Base, available from PV*SOL premium 2023 R5, and the Renusol PV Configurator from PV*SOL premium 2025 R6. For other mounting systems, the layout is planned in PV*SOL and the structural calculation is run separately in the manufacturer’s own software.

Does a K2 Base report meet the MIS 3002 roof check?

Not on its own. The K2 Base report covers the mounting kit and its fixings. MIS 3002 version 6.0, mandatory since 18 June 2026, requires the roof structure itself to be checked by a suitably competent person before installation. The two documents answer different questions, and an MCS installation needs both.

Can I still move modules in PV*SOL after the K2 import?

You can, but you should not. After the import, the layout matches the manufacturer’s structural report exactly. Any change makes the report and the parts list invalid, and PV*SOL does not warn you. If the layout changes, send the affected area through K2 Base again.

Checklist

  • Module type agreed with the client before the first area is exported
  • All obstacles added in PV*SOL, not only in K2 Base
  • Areas named identically in PV*SOL, K2 Base and the title block
  • Layout frozen after the K2 import; changes only through a new round
  • Roof structure check planned for MIS 3002, separate from the kit report
  • DXF measured against two distances; one revision index across all files and the G99 pack