G99 Application: The Drawings Your DNO Needs
October 13, 2026

A G99 application is the connection request you send to your Distribution Network Operator (DNO) before installing generation above 16 A per phase, which is 3.68 kW on a single-phase supply. Alongside the form, the DNO expects drawings: a location plan, a site layout plan and, for anything beyond the smallest systems, a single line diagram. Incomplete drawings are a common reason for applications coming back.
In short
- G98 covers type-tested micro-generation up to 16 A per phase and is notified within 28 days of commissioning. Anything above that needs G99 approval before you connect.
- Form A1-1 covers Type A systems up to 17 kW single-phase or 50 kW three-phase. Form A1-2 covers integrated micro-generation up to 7.36 kW (32 A) where a G100 export limitation scheme caps export at 3.68 kW.
- National Grid Electricity Distribution lists location plans, site layout plans and manufacturer’s specification sheets as the documents you need before you start.
- The single line diagram is the drawing DNOs check most closely. It has to match the form exactly: capacities, inverter models, protection and any export limitation device.
- In our calculation for a site near Birmingham, a 3.68 kW export cap costs a 6 kWp south-facing system 3.6 % of its yield if everything is exported, and an 8 kWp system 12.1 %.
We produce the drawings that go into G99 applications for UK installers: single line diagrams, location and site layout plans, and PV layouts, delivered as DWG and PDF through our AutoCAD solar planning service. The application itself stays with you. This guide covers what each drawing has to show so the DNO can assess it without sending it back.
What is a G99 application?
A G99 application is the request for permission to connect generation or storage to the distribution network under Engineering Recommendation G99, the ENA standard for power generating modules above the G98 limit. National Grid Electricity Distribution states that installations in excess of 16 A (3.68 kW) per phase must comply with EREC G99. Unlike G98, where you notify the DNO after commissioning, G99 needs the DNO’s approval before the system is connected.
Which form you use depends on size and on whether you limit export. Using the wrong form is one of the recurring issues Electricity North West lists in its own G98/G99 application guidance.
| Route | Typical use | Form | Drawings to prepare |
|---|---|---|---|
| G98 | Type-tested micro-generation up to 16 A per phase | G98 Form B, within 28 days of commissioning (Form A for multiple installations) | Keep a single line diagram in the handover pack |
| G99 with G100 export limitation | Integrated micro-generation up to 7.36 kW (32 A), export capped at 3.68 kW | G99 Form A1-2 plus ELS application form | Single line diagram showing the export limitation device and its CT position |
| G99 Type A, small | Up to 17 kW single-phase or 50 kW three-phase | G99 Form A1-1 (A2 compliance forms if not fully type tested), A3-1 at commissioning | Location plan, site layout plan, single line diagram |
| G99, larger systems | Above 50 kW three-phase | Standard G99 application form, Parts 1 to 4 | Location plan, site layout plan, single line diagram, transformer and protection data |
For the wider approval process, including pre-application enquiries and connection offers, see our guide to grid connection approval for solar PV in the UK.
Which drawings does the DNO need for a G99 application?
For a G99 application the DNO needs a location plan, a site layout plan and a single line diagram, together with the manufacturer’s specification sheets. National Grid Electricity Distribution lists the first two and the specification sheets under “Before you start” on its G99 page. The single line diagram is what the engineer uses to check protection, metering and export limitation, and in practice it decides how fast the assessment goes.
| Drawing | What it must show | What the DNO uses it for |
|---|---|---|
| Location plan | Site address and postcode, site boundary, position of the building or field on a map | Identifying the network that serves the site |
| Site layout plan | Array position, inverter and battery locations, cable routes, cut-out and meter position, isolators, export limitation CT | Locating the point of connection and checking access and isolation |
| Single line diagram | Every electrical component from the array to the point of connection, with ratings | Checking capacities, protection, metering and export limitation against the form |
| Specification sheets | Inverter and module datasheets, ENA type test references | Confirming compliance with G98/G99 settings |
What should a G99 single line diagram show?
A G99 single line diagram should show the full electrical path from the PV array to the point of connection, with a rating for every component, so the DNO can check it against the form without asking questions. On our drawings that means the following elements, labelled in the same terms as the application:
- PV array: total capacity in kWp, number of strings and modules per string.
- DC side: DC isolators and, where used, string fuses or combiner boxes.
- Inverters: make, model, rated AC output in kW and the phase each inverter connects to.
- AC side: AC isolator, protective devices and the generation meter.
- Interface protection: where the G99 protection function sits, in the inverter or as a separate relay.
- Battery storage: battery inverter, capacity and coupling, because storage counts towards the declared capacity.
- Export limitation: the limiting device and the position of its current transformer, if a G100 scheme is used.
- Existing generation: any PV, battery or generator already on the same connection.
- Point of connection: cut-out, main meter and MPAN reference.
The detail most often missing is existing generation. If the site already has a system on the same supply, the DNO assesses the total, and a diagram that only shows the new array will not match what is on site. Protection settings follow from the same drawing; our guide to protection relay settings for UK solar PV covers the values that usually need to be stated.
For symbols, battery coupling and multi-inverter layouts, see our guide to the solar single line diagram.
From our projects: a 91 kWp drawing set
For a 91 kWp rooftop system we drew 182 modules of 500 W on one Huawei SUN2000-115KTL-M2 inverter with 115 kW AC output, with the site and string plan, inverter mounting details and module spacing in DWG. The full set is in our 91 kWp AutoCAD case study. A system of this size shows why the capacity figures on the drawing matter: the array is 91 kWp, the inverter is rated at 115 kW, and in the UK either figure is above the 50 kW three-phase limit of Form A1-1, so it would go through the standard G99 application. State both values on the single line diagram, and state the export capacity you are applying for if it is lower.
Need the drawings for a G99 pack? We draw the single line diagram, location plan and site layout as DWG and PDF, ready to attach to your application.
From our calculations: what a 3.68 kW export cap costs
Form A1-2 lets you install up to 7.36 kW if a G100 export limitation scheme keeps export at 3.68 kW, which is often quicker than a full G99 assessment. The question installers then get from clients is how much generation the cap throws away. We took hourly yield data from PVGIS (SARAH3 database, 2020 to 2023, 14 % system losses) for a site near Birmingham, at 35° tilt, and applied a 3.68 kW export limit to every hour.
| System size | South-facing: lost to cap | South-facing: hours above cap per year | East-west: lost to cap |
|---|---|---|---|
| 5 kWp | 31 kWh (0.6 %) | 126 | – |
| 6 kWp | 208 kWh (3.6 %) | 344 | 0 kWh (0.0 %) |
| 8 kWp | 942 kWh (12.1 %) | 753 | 126 kWh (2.0 %) |
| 10 kWp | 2,011 kWh (20.8 %) | 1,074 | 516 kWh (6.7 %) |
Two things stand out. Up to about 6 kWp facing south, the cap costs little; above that, losses climb quickly, to 12.1 % at 8 kWp. An east-west layout of the same size loses far less, because it rarely reaches the cap at midday. These figures are the worst case: self-consumption and a battery absorb part of the midday peak, so real losses on a house or business with daytime load are lower. Hourly averages also smooth short peaks, so a minute-resolution simulation will show slightly higher curtailment than this table.
For a client-specific answer, model the export limit in the simulation with the client’s load profile. Our PV*SOL planning service includes the export-limited variant in the report, and the guide to inverter sizing and configuration explains how the inverter rating interacts with the cap.
How long does a G99 application take, and what does it cost?
Timescales and costs depend on the DNO, the size of the system and whether the local network needs reinforcement. Small Type A applications with complete, type-tested equipment are usually the fastest. Larger connections can attract Assessment and Design fees, which DNOs publish under their connection offer expenses rules, and where reinforcement is needed the offer can take months.
Published figures from installer websites vary widely, so we do not quote them here. Two things you control do shorten the process: the correct form for the route, and drawings that match the form. Electricity North West, for example, notes that a missing Manufacturer’s Reference Number from the ENA Type Test Register stops it from confirming compliance. For larger sites, check the fault level early; our article on fault level assessment for UK solar grid connections explains why.
Common mistakes
- Wrong form for the route: an A1-1 sent where an export-limited A1-2 would apply, or the reverse. Fix: decide on export limitation before you start the paperwork.
- Capacities that do not match: kWp on the drawing, kW AC on the form, a different figure in the datasheet. Fix: state both DC and AC capacity on the single line diagram.
- Existing generation or storage left off the diagram. Fix: survey the existing installation and draw it.
- Export limitation device not shown, or no ELS application form attached. Fix: draw the device and its CT position, and attach the DNO’s ELS form.
- Missing Manufacturer’s Reference Number. Fix: look up each inverter on the ENA Type Test Register before filling in the form.
FAQs
What is the difference between G98 and G99?
G98 covers type-tested micro-generation up to 16 A per phase, and you notify the DNO within 28 days of commissioning. G99 covers everything above that limit and needs the DNO’s approval before connection. On a three-phase supply, the G98 limit applies per phase, so more capacity fits under G98 than on a single-phase supply.
Who submits the G99 application?
The application is completed by the applicant or the installer and sent to the DNO for the area where the system will be connected. A design office can prepare the drawings and data sheets that go with it, but the declaration on the form is signed by the applicant or installer.
Can I install more than 3.68 kW without a full G99 assessment?
Often, yes, if you limit export. Electricity North West’s guidance describes Form A1-2 for integrated micro-generation up to 7.36 kW (32 A) with a G100 export limitation scheme capping export at 3.68 kW. Check your own DNO’s form, because the conditions differ slightly between networks.
Does a battery count towards the G99 capacity?
Yes. Electricity storage connected to the network is treated as generation for the application, so the battery inverter must appear on the form and on the single line diagram. Leaving it out is one of the mismatches that sends applications back.
Checklist
- Decide the route first: G98, G99 with export limitation, or full G99.
- Download the current form from your DNO, not a copy from a previous job.
- Prepare the location plan, site layout plan and single line diagram, including existing generation and storage.
- Look up the Manufacturer’s Reference Number for every inverter.
- If you use export limitation, model the cap with the client’s load profile and attach the ELS form.
We draw single line diagrams, location plans and site layouts for G99 applications as DWG and PDF, labelled to match your form, so your application goes in complete.
Author: Heval Arcan, Lion Solar Solutions. As of October 2026.